Development of the Product
- How sound are the scientific principals
underlying this invention?
- There are serious questions as to the
soundness of the science.
- Most of the scientific principals have
been proven and our judgment is that the remainder will
be proven upon further work.
(10) The science is sound and has
been proven either in this effort or previous
documented efforts.
- In what stage of development is this
product?
- It is on paper only and is at a very high
level.
- It has progressed past the proof of
principal stage and all engineering/scientific principles
have been proven. A dependable schedule for completing
development is in place.
(10) It is ready for production
and pre-production prototypes are available.
Product cost estimates are in place and are firm.
- What is the capability to develop
derivative products from this technology?
- No derivative products appear to be
possible.
(5) Opportunity exists to make
this a platform for multiple products.
Substantial engineering resources will be
required. No solid product plans are in place for
derivatives.(10) This
technology is a platform for multiple products. A
number of product plans are in place. A high
degree of reuse of engineering work is possible.
- What is the length of time required for
regulatory approvals?
- Regulatory approvals are expected to take
more than two years.
(5) Regulatory approvals are expected to
take less than one year.(10)
There are no regulatory approvals required.
- What is the degree of development risk in
this project?
- There is a high likelihood that this
project cannot be completed at all or will require
substantially more time and money than planned. The
severity of the cost and time overruns is such that the
opportunity for the product may be lost. The point of
highest risk will be late in the development cycle.
- There is some likelihood that the project
cannot be completed at all but we view the risk as
manageable. Additional time and money above budget may be
required but we believe these amounts will not jeopardize
the viability of the product. The point of highest risk
is in the early half of the project.
(10) It is virtually certain that
this project can be completed on time and within
budget. We have passed the point of highest risk
and the remaining risk is contained.
- What is the remaining time to market?
- The remaining time to market is over three
years.
- The remaining time to market is 18-36
months.
(10) The remaining time to market is less
than 18 months.
- What development investment in dollars is
required from now to first customer shipment?
- More than $2 million
- Between $1 and $2 Million
(10) Less than $1 million
- What development personnel resources are
required and how readily available are they?
- Greater than 15 development personnel will
be required and none of them are believed to be readily
available.
(5) 10-15 development personnel will be
required, a large percentage of them are on staff and the
remainder is believed to be readily available.(10) Less than 10 development personnel will be
required and all are on staff, or more than 10 will be
required and all are on staff.